Gordon and Rees Home Our Practice Areas
 

Our Practice Areas: Publications

Gordon Endow

Article RE Geotechnical And Environmental Pre-Construction Contracts For ABA Forum On Construction Fall Meeting, Tampa

October 2004

By Kenneth F. Strong
send email

When a Developer or Owner first contemplates constructing a project on a particular site, it is necessary to obtain basic information about the site before any design work can commence.  Some of this work may take place before the Developer even acquires an interest in the land on which the project is to be sited.  The Developer needs to explore local zoning and land use restrictions, the General Plan for the locality as well as other regulatory requirements to determine if the project he is contemplating is permissible on that site or whether it will be necessary to obtain changes or variances from local officials. 

Assuming these obstacles are not insurmountable, the Developer next must investigate the existing condition of the earth and any structures on the site to determine how those conditions will impact the feasibility and cost of its proposed project.   The two concerns most likely to impact the project are the presence of environmental contamination on the site and the geological and geotechnical conditions of the ground on which the project is to be founded.  The presence of either environmental contamination or atypical soils conditions, if not discovered in advance of project design and commencement of construction, have the potential to adversely impact project costs greater than virtually any other factor affecting a project.

A few examples will illustrate this circumstance.  An owner decided to construct a hotel with a four story underground basement near the beach in an urban area.  During the geotechnical investigation prior to design, the soils engineers unexpectedly encountered concrete obstructions in two of the soil borings.  Speaking to a long time local resident, the engineers were told that there was previously a commercial swimming pool in that location.  The engineers reported that finding and proposed additional investigation to verify that finding.  The owner decided not to incur that cost.  When construction commenced, the excavation contractor found an intact two story basement structure.  The cost of the excavation tripled as did the length of time to complete the excavation phase.  In this case, because the contract contained a clause whereby the contractor waived claims for differing site conditions, the contractor saw his entire profit for the project disappear into the ground.  The contractor cut corners on the remainder of the project and was eventually terminated. The delays in construction, cost increases incurred through changing contractors and other project cost overruns forced the Owner into bankruptcy before the project was completed.  All of this started with unanticipated subsurface conditions.

A Developer identifies a rural site for development as single family homes. It retains a consultant to prepare a Phase I ESA.  The consultant does so and follows the ASTM procedures including a review of applicable public records and aerial photographs.  The consultant does a walk around but the current owner is absentee and knows little about the site. Based on available information, the consultant opines that there is no evidence of hazardous materials on site.  In reliance on that report, the Developer acquires the site. After property acquisition and during construction, the contractor discovers a substantial quantity of lead shot from an old shooting range. Construction is suspended while environmental sampling is conducted and regulatory officials review the collected data. The result is that a substantial portion of the site cannot be developed for residential use unless a large quantity of contaminated soil is hauled off to a Class 1 landfill at considerable expense rendering the project no longer commercially viable.

In another example, in connection with the acquisition of a former shipbuilding property, an environmental consulting firm conducted a Phase II investigation and issued a report outlining the known contamination.  During construction, the grading contractor unknowingly began distributing “reddish dirt” around the site.  The “reddish dirt” turned out to be contaminated with lead based paint.  In a subsequent cost recovery action under CERCLA, the grading contractor was held to be an operator and a transporter under CERCLA.1 The grading contractor in turn cross-complained for indemnity against the environmental consultant claiming that the consultant was negligent in failing to identify the paint contaminated soil.  While the Court held the consultant did not owe a duty of care to the grading contractor with whom it was not in privity, the consultant could have been successfully joined by its client in that action.

Because of the substantial risks associated with unanticipated environmental contamination or soil conditions, the contractual arrangements under which geotechnical engineers and environmental consultants perform the appropriate site investigations are critical.  They are not typically included in the package of standard form agreements put out by AIA, AGC or DBIA because they are usually direct contracts between Owners and the responsible engineer or consultant. The AIA does provide a form for owners to use2, but in the 20 years I have been representing geotechnical engineers I have never seen that form used.  

ASFE:  Professional Firms Practicing in the GeoSciences, a trade organization of engineering firms providing geotechnical and environmental services have developed contract guides for their member firms but do not provide sample contract forms.  Companies that provide insurance to geotechnical and environmental firms such as XL DP and Terra Insurance provide contract reference guides but not complete contract templates.

The purpose of this article is to provide some proposed form agreements and to discuss the most important clauses in those agreements. First however I will provide a context concerning the purpose and scope of a typical geotechnical investigation and preliminary environmental site assessment so put the contract terms in perspective.

The Purpose and Scope of a Typical Geotechnical Investigation

Whenever a structure is constructed it imposes certain loads on the earth.  If the structure is built on bare bedrock, presumably the bedrock will provide sufficient support that the structure will not undergo any movement or shifting during its useful life.  However the vast majority of structures of course are not directly on bare bedrock but rather on top of the soil overburden.  Depending upon the geological characteristics of the soil and its thickness, the soil will provide varying degrees of support for a structure.  Frequently the soil is not uniform and therefore the differing geological composition of the soil and the thickness of the different layers or lenses of soil will provide different amounts of support for the structure built on those soils. The depth to groundwater may also play a role in the manner in which the earth supports a structure. Further, while to a layman the difference between rock and soil may seem clear, there is in fact a continuum between what we understand as solid rock and sand or silt. Certain types of soils, particularly clays, are highly expansive.  This means that they swell when they get wet and shrink as they dry out.  Structures built on highly expansive soils can experience heave.  Structures that are not properly supported on compressive soils such as mud can experience differential settlement where portions of the structure may settle as much as 1-2 feet relative to other portions of the structure.  In the worst cases, the structure may even collapse.

It is the province of the geotechnical engineer to assess the ability of the site soils to support the proposed structure.  They do this by drilling a number of soil borings to sample the subsurface conditions.  They remove core samples from the borings and subject the samples to tests to determine the strength, plasticity, moisture content  and composition of the soils.  The analysis of these test results and the assessment of the bearing capacity of the tested soils is called soil mechanics.  The geotechnical engineer than extrapolates between the data points(borings) to provide a professional opinion concerning the soil conditions beneath the proposed structure and recommendations as to the appropriate foundation system to support the loads anticipated by the project structural engineer. Foundation types range from slab on grade to spread footings to pile supported structures. 

While geotechnical engineers are now able to provide reliable scientific judgments as to how the particular soils sampled from a site and tested will perform when subjected to building loads and stresses, the ability to predict with a high degree of accuracy the soil characteristics on a site with any degree of variability is more problematic. It is noteworthy that even for the most experienced geotechnical engineers, characterizing subsurface conditions and interpolating between boring locations remains a matter of engineering judgment.  “Although soils mechanics has become a science, subsurface soils investigation by soil boring techniques is still an art.”3  Indeed the practice of geotechnical engineering is somewhat akin to drilling holes in a book and trying to read the book’s text by peering down those holes. 

For that reason it is important that all of the participants in a construction project understand the uncertainty and risks of unanticipated subsurface conditions and contract with each other in a way to properly allocate those risks among those not only best able to manage the risk but also with an eye toward the financial rewards of a successful project.

The Purpose and Scope of a Typical Phase I Environmental Site Assessment

A Phase I Environmental Site Assessment (ESA), is a somewhat analogous exercise attempting to understand whether or not a site is contaminated based on a limited amount of data.  The standard of care for an ESA has been largely standardized by ASTM.  The purpose of an ESA is to identify without undertaking any subsurface investigation whatsoever, whether it is likely that a site is contaminated.  The scope of a typical ESA involves four tasks: (1) A review of historical aerial photographs, Sanborn maps and other public records to attempt to determine past uses of the site no longer apparent through a visit to the site; (2) Interviews of current owners, tenants and in some cases neighbors in order to develop an understanding of past and present uses of the site and uses of hazardous materials on and in the immediate vicinity of the site; (3) A visit and walk through inspection of the property looking for visible signs of the use of hazardous materials, the existence of underground storage tanks, or evidence of discoloration of soils reflecting past releases of contaminants; and (4) A data base search of the records of regulatory agencies to determine whether the site or other sites in the vicinity have had reported releases of contaminants to the soil or groundwater.  An ESA may or not contain conclusions and/or recommendations for further investigation depending upon the contracted for scope of work.  Where evidence of present or past contamination is known or suspected the consultant will typically recommend a Phase II Investigation which will consist of a program of soil, soil vapor or groundwater samples to determine the presence and concentration of contaminants.  Again, it is a limited investigation from which the consultant can develop professional opinions about the nature and extent of contamination at the site.

ASFE, a trade organization of consulting firms, as well as the major insurers issuing policies to environmental consulting firms have identified Phase I ESA’s as the professional service that gives rise to the greatest frequency of claims against their member firms.  ESA’s are typically low cost, low profit-margin jobs often with a very short turn around time.  Frequently clients incorrectly view this service as a commodity and look simply for the lowest cost provider.  Some clients and lenders look at the consulting firms as an insurance policy against unanticipated remediation costs.

With that background lets turn to the key clauses in a contract for geotechnical engineering services from the perspective of the engineer.

Scope of Work

The services to be performed by the geotechnical or environmental consultant are among the most important provisions of the contract as they set forth the consultants and clients agreement as to extent of the investigation that will be undertaken to best meet the clients need to reduce the uncertainty as to subsurface conditions at a manageable cost.  The number of borings necessary to adequately characterize a site is a matter of professional judgment depending upon what is known about the site from previous nearby investigations, published geologic maps, the details of the proposed project and the owner’s budget.  It is important for the engineer to explain and the Owner to understand that geotechnical engineering is more an art than a science when it comes to predicting subsurface conditions in areas where there is significant geologic variability.  An analogy I have used is that investigating a site is something like drilling holes through a closed book and trying to understand the theme of the book based on the words or letters you can see peering down those the holes.  The more holes you drill the better understanding you have of the book but that understanding remains imperfect and subject to error.

Depending upon the project, some clients may be content to contract for a limited investigation understanding that this will increase the risk of unanticipated subsurface conditions the risk of which will be managed by contingencies in the construction contracts or a project design that is less likely to be impacted by variable soil conditions across the site.  Other owners may want to conduct extensive subsurface investigations either because that is necessary for purposes of building design or in order to provide contractors with sufficiently detailed information so that contingencies are reduced or eliminated.

In order to properly document the clients involvement in the decision as to the appropriate scope of work, it is preferable to detail the scope of work in a proposal letter to the client which includes a discussion of the trade-offs that have been discussed with the client and the decision on scoping.  The letter should reference not only the tasks that the engineer/consultant is going to perform but also those tasks that are frequently performed on similar projects that pursuant to discussions with the client are not going to be performed.  This proposal letter is then referenced as an Exhibit to the contract with the client and incorporated by reference.

Standard of Care

Professional Engineers and Consultants may be held liable if they fail to comply with the applicable professional standard of care and someone is damaged or injured as a result.  The failure to meet the standard of care creates liability under common tort law.  That liability is described as professional negligence.  Although the phrasing may differ slightly from one jurisdiction to another, the following approved California Jury Instruction is illustrative of how the term “standard of care” is applied by courts throughout the country.

An engineer performing professional services for a client, owes that client the following duties of care:

1.         The duty to have that learning and skill ordinarily possessed by reputable engineers, practicing in the same or a similar locality under similar circumstances;

2.         The duty to use the care and skill ordinarily exercised in like cases by reputable members of the profession practicing in the same or a similar locality under similar circumstances; and

3.         The duty to use reasonable diligence and his or her best judgment in the exercise of skill and the application of learning.

A failure to perform any one of these duties is negligence4

This standard of care does not require an engineer or consultant to guaranty or insure the results of his or her professional efforts. Unless the professional by contract guarantees or warranties a particular result, the failure to achieve a desired result in the design is not necessarily negligence. California juries are instructed on this point as follows:

An engineer is not necessarily negligent because he or she errors in judgment or because his or her efforts prove unsuccessful. However, an engineer is negligent if the error in judgment or lack of success is due to a failure to perform any of the duties as defined in these instructions.5 

The same standard of care applies whether the project is for a private client or for a public entity. In a case involving an architect, the Board of Contract Appeals for the Corps of Engineers described the obligations of a design professional in the following manner:

It has been said that an architect will be held liable for damages sustained by his employer where, by reason of the architect’s breach of his duty to exercise care and skill, his plans and specifications are faulty and defective.  However, in the absence of any special agreement in that regard, an architect’s undertaking does not imply or guaranty a perfect plan or satisfactory result and there is no assurance that miscalculations will not occur.  Liability rests only on unskillfulness or negligence and not upon their errors of judgment.6

Design Professional Insurance Company (D.P.I.C.) states the concept slightly differently.

As a design professional, you are subject to the doctrine of professional negligence.  Established in common law, it requires you to maintain a professional standard of practice, i.e. that level of professional skill and competence ordinarily and contemporaneously demonstrated by members of your profession in the area where you practice.  Simply committing an error or omission is not necessarily a negligent act.  You are human; humans make errors; errors are allowed.  If the error resulted because you failed to exercise ordinary skill or care, however, and if someone is damaged or injured as a result, then negligence exists.”

The Minnesota Supreme Court in City of Mounds View v Warlijarv discussed the rationale behind the standard of care. 7

Architects, doctors, engineers, attorneys and others deal in somewhat inexact sciences and are continually called upon to exercise their skilled judgment in order to anticipate and provide for random factors which are incapable of precise measurement. The indeterminate nature of these factors makes it impossible for professional service people to gauge them with complete accuracy in every instance. Thus doctors cannot promise that every operation will be successful; a lawyer can never be certain that a contract he drafts is without latent ambiguities; and an architect cannot be certain that a structural design will interact with natural forces as anticipated. Because of the inescapable possibility of error which inheres in these services, the law has traditionally required, not perfect results, but rather the exercise of that skill and judgment which can be reasonably expected from similarly situated professionals.

The professional standard of care to which an engineer or consultant’s performance is compared, is that standard of care which existed at the time that the work was performed.  An engineer or consultant need not anticipate advances in technology or in the “state of the art”.  This is particularly important in fields such as environmental assessment and remediation, where the professional standard of care is constantly evolving.

In an excellent discussion of the judgments and trade offs that apply to geotechnical engineers, Steven Stein and Carl Popovky in an article titled Design Professional Liability for Differing Site Conditions and the Risk Sharing Philosophy that appeared in the April 2000 issue of The Construction Lawyer point out the degree of judgment involved in geotechnical engineering.  They note, ‘[a] fundamental problem is that the present state of the art simply has not advanced sufficiently to allow designers to reasonably predict some of the most basic conditions under which the contractor will perform its work.”  These limitations on the ability of geotechnical engineers to predict with accuracy subsurface conditions will lead to overly conservative design recommendations unless the contract provides a fair risk allocation.

Some clients seek to commit consultants contractually to perform to “the highest standard of the profession” or the equivalent.  This can present substantial problems for the engineer or consultant in the event of claim.  First, while there is a general understanding of the concept of a reasonable standard of care and the kind of expert testimony required to prove a breach of the standard of care and thus negligence, there is no such body of case law or general understanding as to what is necessary to prove that an engineer or consultant either met or failed to meet “the highest standard of the profession”.  Is that the equivalent of the state of the art?  Does it impose a nationwide standard as opposed to the more localized focus in a traditional standard of care analysis in most jurisdictions?  Has a plaintiff met its burden if it produces expert testimony that somewhere in the country another engineering firm drilled more exploratory borings on a similarly sized site, or conducted additional soil mechanical tests?  Is the highest standard the most conservative design, the most cost effective design, the most innovative design?  All of these are uncertainties facing the parties contracting under such terms.

Of potentially greater significance to both parties is the effect of such a clause on insurance coverage.  One policy covering professional errors and omissions contains a coverage grant  agreeing to pay “…DAMAGES and EXPENSES caused by YOUR PROFESSIONAL ACTS, ERRORS OR OMISSIONS.  It defines YOUR PROFESSIONAL ACTS, ERRORS OR OMISSIONS as follows:

N. “PROFESSIONAL ACTS ERRORS OR OMISSIONS” means YOUR negligent acts, errors or omissions in YOUR performance of YOUR usual and customary professional services or a series of such related professional services in YOUR professional capacity, rendered subsequent to the Retroactive Dates(s) as set forth in the GENERAL DECLARATIONS.  Items 8 and/or 9, as applicable, which result in a CLAIM.

If the engineer or consultant performs their work in a manner that is non-negligent, i.e. consistent with the common law standard of reasonable care, but is adjudged to have failed to meet the “highest standard of the profession”, there is a risk that the policy will be held not to provide coverage for the claim.  This is obviously not in the interest of either the engineer/consultant or the client. 

Pricing and Payment

Geotechnical engineers and environmental consultants generally provide services under one of two compensation schemes:  lump sum, or time and materials.  Where the payment method is lump sum the contractual issues are generally the same as those found in traditional Owner/Architect agreements or Owner/Contractor agreements; pay if paid/pay when paid clauses, payment application processes, retainage, and the right to offset actual or potential claims against payments owed.

Where the services are to be performed on a time and materials basis, the contract almost always includes a dollar amount beyond which the engineer or consultant will not be compensated without further client authorization.  The most common ambiguity in these provisions is a lack of clarity as to the relationship between the specified dollar amount and the engineer or consultants obligation to complete the scope of services described in the contract.

For example, contracts frequently contain the following or substantially similar language:

Consultant shall perform the services described in the attached proposal on a time and materials basis, not to exceed  $__________ without Clients express written approval.”

From the viewpoint of the consultant, the “not to exceed” dollar amount in the above clause is a target budget.  The consultant understands that they will not be paid if they bill in excess of that budget amount without first obtaining client approval to increase the budget.  On the other hand, the consultant does not feel contractually obligated to complete all services identified in their proposal for this “guaranteed maximum price”.

In contrast, the client may view the above clause as establishing a guaranteed maximum price contract.  If the cost to complete the identified scope of services is less than the “not to exceed” dollar amount stated, than the client gets the benefit of the cost savings.  If on the other hand the cost to complete the contracted for scope of work is greater than the “not to exceed” amount, the risk of that additional cost is to be borne by the engineer or consultant.

While either approach may be satisfactory to the parties, what is critical is that the contract language clearly expresses the intent of the parties.  If the “not to exceed” dollar amount is intended to place the risk of cost overruns on the engineer or consultant, the payment provision should be clearly labeled as a “Guaranteed Maximum Price”.  Alternatively, if the “not to exceed” number is a target budget, the contract should use the term budget and should contain a parenthetical phrase stating that because of potential uncertainties in the work, the consultant is not guaranteeing that it will complete the scope of services described within the budget amount but will not invoice in excess of the budget without the written authorization of the client.

Indemnity/Liability Assumed by Contract

Geotechnical engineers and environmental consultants face the same issues relating to indemnity as do most design professionals.  Indemnity clauses that seek to hold the engineer or consultant liable for damages beyond those caused by the engineer or consultant’s negligence are frequently not insurable. This is different from the typical insurance coverage afforded under a Comprehensive General Liability policy.  This difference is highlighted by the prevailing practice of professional liability insurers to refuse to issue additional insured endorsements.

It is beyond the scope of this paper to undertake a coverage analysis of professional liability policies.  However in general terms, professional E&O policies do not cover liability assumed by contract that is greater than the liability the insured would have under the law in the absence of the contractual indemnity provision.  These policies do not cover the cost of defending a client against claims beyond the comparative negligence of the insured.  Thus most carriers refuse to pay for the cost of retaining separate counsel to defend a client.  If there is a judgment against an insured and its client the clients defense costs may be covered as compensable damages flowing from the negligent conduct of the insured, but such defense costs will not be paid by the carrier during the course of the litigation.

Similarly, where a design professional agrees to indemnify a client under a Type 1 indemnity agreement and thus is responsible contractually for the clients proportionate fault unless the client is solely negligent, the E&O policy does not cover the clients proportionate fault. 

The result of these limitations on insurance coverage is to create a significant uninsured potential liability when engineers and consultants agree contractually to broad indemnification language.  Where a claim is complex and the litigation contentious, this uninsured exposure could exceed the firms available resources.  As the current insurance market has driven up deductibles, it is conceivable that a modest sized engineering or consulting firm with a deductible of $100,000-$150,000 might find that the cost of funding the client’s uninsured contractual defense makes it impossible to pay the deductible.  Under that scenario, the client’s insistence on having its defense paid for might prevent the design professional’s E&O coverage from being triggered.

Even where the insurer does provide coverage for the defense obligation (often under a reservation of rights) such clauses are particularly problematic for design professionals in a way different from the impact of such clauses on contractors.  That is because most professional liability polices provide that the policy limits are eroded by defense costs.  Without an additional insured endorsement, the professional liability insurers will almost always refuse to pay for the defense of the client no matter what claim is asserted.

Waiver of Consequential Damages

A waiver of consequential damages provision is even more important for geotechnical and environmental consultants than architects or contractors.  In the first instance, like other design professionals, geotechnical and environmental consultants rarely sustain substantial consequential damages even if a project is significantly impacted by owner caused delays.  The time in the field necessary to conduct a geotechnical investigation is a few days or weeks at most.  There is little if any equipment that remains on site as the investigation is customarily conducted with a mobile drilling rig that is not a particularly expensive piece of equipment that can be easily removed from the site and returned without substantial mobilization or demobilization costs.  Personnel can be shifted to other projects with relatively little delay or impact.

In contrast, the potential impact to contractors or owners from project delays resulting from inaccurate subsurface investigations can be quite substantial and out of all proportion to the consultants fee or even the costs directly related to account for the unanticipated conditions.  One need only think of the lost revenue or profits from a substantial delay in the scheduled opening of a casino or “Big Box” retail store to understand how consequential damages can quickly dwarf the direct project costs of unanticipated subsurface conditions.

Limitations of Liability

From the perspective of a geotechnical engineer or environmental consulting firm, Limitation of liability clauses are often one of the most critical terms of a contract.  The reason for this should be readily apparent.  The typical soil investigation and resulting report for a project costs in the range of $__________.  The profit margin for engineering firms ranges typically from 5% to 10%.  Assuming conservatively total billings for a soil investigation of $100,000 and a profit margin of $10%, that leaves the firm $10,000 in profits for a project.  Phase I Environmental Site Assessments frequently cost no more than $5000 and have a similar profit margin.  There simply is no way that a firm can survive if it places the company’s entire assets at risk on each and every project when the rewards of a successful project are so relatively modest when compared to the other project participants.

For that reason, many engineering and consulting firms require some limitation of liability provision in their contracts or have in place stringent internal procedures that must be followed before they will sign contracts without a limitation of liability provision. Alternatively, such firms may insist upon significantly greater mark ups or a much more extensive scope of work for the investigation or a more conservative foundation design where clients are unwilling to agree to limitation of liability clauses.

A limitation of liability clause is neither exculpatory, nor does it indemnify the design professional.  It merely serves to cap the potential financial exposure of the design professional in the event that the design professional is liable for either negligence or breach of contract.  Limitation of liability clauses in engineering contracts have been upheld as enforceable in  a number of jurisdictions including California, New Jersey, Washington, Texas, Pennsylvania, Florida, Georgia, and New York. 

A. California law

Generally, provisions limiting liability in construction contracts are enforceable under California law so long as the parties negotiated and expressly agreed to the limitations, and the provision is not against public policy.8

There is only one published case in California addressing the issue of limitation of liability clauses in a designer’s contract.  That case is Markborough California, Inc. v. Superior Court.9

In Markborough, a developer brought an action for breach of contract against an engineering firm arising from the failure of a lake liner designed by the defendant.  The trial court granted defendant’s motion for summary adjudication, determining that a limitation of liability clause in the contract between the parties was valid, and that defendant’s liability was limited to $67,640 as stated in said clause.  Plaintiff petitioned for writ relief.  In its petition, plaintiff contended that the limitation of liability clause was invalid because it had not been negotiated and expressly agreed upon by the parties, as required by Civil Code § 2782.5.

In denying the petition, the Court of Appeal rejected plaintiff’s “contention that the phrase ‘negotiating and expressly agreeing’ imposes upon parties such as [defendant] the affirmative duty to specifically advise the other party of the inclusion of a liability limitation clause in the contract and to inform the other party of the risks involved in the project.”10  Rather, the Court held “that ‘negotiating’ as used in § 2782.5 and applied to a particular contract containing a limitation of liability clause simply means that the agreement was reached between parties wherein each party had an opportunity to accept, reject or modify such a provision.  If the parties had such an opportunity with respect to the provision, the provision is valid even if there is no actual discussion regarding the provision but rather it is simply proposed and accepted.”11  In conclusion, the Court noted that plaintiff “agreed, whether knowingly or simply because it failed to read the contract, to assume the risk of most of the economic loss which might result from [defendant’s] negligence in exchange for a consulting fee acceptable to it.  There is no justification for allowing [plaintiff] to shift this loss to [defendant] which neither agreed to assume it nor was compensated for such assumption.”12

Essentially, the court held that two prongs must be met before a limitation of liability provision in a construction contract will be enforced.  The first is that the contract limiting the liability must have been negotiated.  The court specifically rejected the argument that “negotiation” meant that the party had to specifically advise the other party of the potential risks involved by agreeing to the limitation.  The court held that had that been a requirement, the Code would have so stated.  The court then defined “negotiate” as meaning a “fair opportunity for both parties to accept, reject or modify the other’s offers or demands.”13 

In Markborough, the court held that the fact that the proposed contract was accompanied with a letter that stated “[i]f the contract documents are acceptable to you, we can begin work as soon as we receive a copy of the signed contract.  We would, of course, have to approve any requested changes before proceeding,” was sufficient evidence to demonstrate a negotiation took place.14 

Moreover, after examining the legislative history of § 2782.5, the court affirmed the generally accepted rule that a limitation of liability provision will be enforced unless the provision is unconscionable or otherwise against public policy.15  Therefore, the second requirement set forth in Markborough is that the contract must not be against public policy or unconscionable.  In Markborough, the court stated that one factor in determining unconscionability is whether the contract was a result of an arm’s length transaction between the parties.  An exculpatory clause can be deemed to be unconscionable based upon the unequal bargaining power of the parties.  The parties are bound by the terms of the contract even if they do not read it.16   Where the parties are both sophisticated entities they presumably negotiated the contract at arm’s length with equal bargaining power on both sides.  The limitation of liability provision is simply one of the bargained for provisions contract and should be enforceable. 

B. Out of State Authority

The U.S. Court of Appeals for the Third Circuit provides a thoughtful analysis of whether limitation of liability provisions contravene public policy under the law of Pennsylvania in Valhal Corp. v. Sullivan Associates, Inc. 17Limitation of liability clauses are not disfavored, especially when contained in contracts between informed business entities dealing at arm’s length, and there has been no injury to person or property.  Limitation of liability clauses are a way of allocating “unknown or undeterminable risks,” and are a fact of every-day business and commercial life.  So long as the limitation which is established is reasonable and not so drastic as to remove the incentive to perform with due care. 

Though it is possible that an agreement setting damages at a nominal level may have the practical effect of avoiding almost all culpability for wrongful action, the difference between the two concepts is nevertheless a real one.  The distinction becomes more apparent in a situation which the damage level is substantial rather than minimal.

Any agreement must spell out the intention of the parties with particularity.  In Valhal, Sullivan Associates, Inc. (“Sullivan”) was exposed to liability which was seven times the amount of the remuneration under its contract with Valhal.  Sullivan’s total fee was $7,000.  Sullivan’s limitation of liability was $50,000.  Accordingly, the cap did not immunize Sullivan from the consequences for its own actions.  It was a reasonable allocation of risk between two sophisticated parties and did not run afoul of the policy disfavoring clauses which effectively immunize parties from liability.

According to the court in Valhal, the inquiry must be whether the cap is so minimal compared to the expected compensation as to negate or drastically minimize concern for the consequences of a breach of its contractual obligations.

Likewise, in Marbro, Inc. v. Borough of Tinton Falls,18 the court decided on summary judgment that a limitation of liability clause in a contract between a municipality and an engineer was enforceable.  There, the clause limited the engineer’s damages for “professional negligent acts, errors or omissions” to $32,500.  Id. at 418.  This figure represented the engineer’s total fee for services rendered under the contract. 

Relying heavily on the Valhal analysis, the New Jersey Court held:

“The limitation of liability clause (paragraph 13) in question does not shield [the engineer] from all professional liability for professional negligence.  If it is determined that [the engineer] acted in a negligent manner, the firm may be held liable for up to $32,500.  This figure represents [the engineer’s] total fee for services rendered under the construction contract.  As expressed by the court in Valhal Corp., the appropriate inquiry is whether the cap is so minimal compared with the expected compensation, that the concern for the consequences of a breach is drastically minimized.  In the instant matter, [the engineer] stands to lose its total fee for services rendered if negligence is found.  This is not a liability cap so minimal compared with the expected compensation as to minimize [the engineer’s] concern for the consequences of a breach of its contractual obligations.  The agreed-upon cap provided adequate incentive to perform.”19 

The court further held that the clause was clear and unambiguous and enforceable as a matter of law.  Id. at 164.  Summary judgment was granted in favor of the engineer enforcing the limitation of liability clause. 

One shortcoming of limitation of liability clauses is that they are generally only enforceable against the party with whom the engineer or consultant contracted.  Thus they provide no protection or limitation on claims by third parties such as the owners of residential units sold by a developer or contractors in those states where the economic loss rule does not bar contractors direct claims against the designer.  There is also some question as to whether limitation of liability clauses provide any protection against claims for indemnity by other parties sued by the client. Certainly such third parties have not contracted to limit their right to recover from the designer.  Yet it does not seem equitable for a party to negotiate a contract with a limitation of liability provision that presumably resulted in a cost savings to be able to avoid that provision by suing another party that is jointly and severally liable for the injury.

There is some case law that supports limiting indemnity claims by third parties where there is a contractual limitation of liability.  The theory is that the party seeking indemnity is in essence seeking to recover for damages claimed by the Client who contracted for the limitation.  Faced with an indemnity claim, the designer has the right to raise any substantive defense against the party seeking indemnity as it would against its client.20.

In the Western Steamship case, plaintiff sustained injury while on board a ship and her injuries were allegedly compounded when she was later taken to a hospital on shore.  At trial, plaintiff recovered damages from the ship owner; the ship owner then sought indemnity from the hospital.  The hospital asserted the liability limitation on damages for emotional distress  contained  in the California Medical Injury Compensation Reform Act (“MICRA”)21.  The California Supreme Court held that MICRA limits applied to indemnity, as well as direct claims.  In reaching this holding, the Court first noted that “as against the indemnitee, the indemnitor can invoke any substantive defense to liability that would be available against the injured party.  Id. at 114.   Second, the Court explained that the right to indemnity is “wholly derivative and subject to whatever immunities or other limitations on liability would otherwise be available.”  Ibid.  The Court also recognized that “whenever one concurrent tortfeasor is insolvent or immunized, either partially or completely, from liability, the remaining tortfeasors must pay more than an amount measured by their proportional responsibility for the injury.  Id. at 117.  See also, Trammell v. Western Union Tel. Co. (1976) 57 Cal.App.3d 538 (agreed limitation liability applies to third party); Colich & Sons v. Pacific Bell (1988) 198 Cal.App.3d 1225 (liability limitation applies to party seeking indemnity).

Third Party Reliance

One of the most common claims against environmental consulting firms over the past fifteen years are claims for professional negligence or negligent misrepresentation by third parties who have obtained copies of Environmental Site Assessments (ESA) from Clients or other sources and assert that they have purchased property in reliance upon what they contend are negligent assertions in the ESA concerning the environmental condition of the property.  Similar claims are asserted against geotechnical engineers by third parties purchasers of development opportunities who argue that a geotechnical report improperly characterized subsurface conditions resulting in increased development costs or lost development opportunities.

Other claims may come from lenders who contend that they loaned money to acquire the property based on representations in the environmental or geotechnical reports and that as a result of subsurface conditions not disclosed in the reports the property is not worth the amount loaned.

There is a substantial amount of case law discussing the obligations of providers of professional information to third parties with whom they are not in contract22.

In order for the engineer or consultant to properly protect itself from third party claims it is critical that the contract clearly identify for whom the report is being prepared, those entities who are entitled to rely upon the report, and protections for the engineer or consultant in the event the report is provided to third parties without the written consent of the engineer or consultant.  Requiring written consent of the engineer or consultant is critical because it allows the engineer or consultant to take steps to educate the client and third parties of any limitations on the report as drafted due to the passage of time, cost or scope limitations on the original report, or the inapplicability of the report for the project or use intended for the property by the third party.

Certifications, Guarantees, Warranties and Representations

It is not unusual on projects where the geotechnical engineer is providing construction phase observation services for the owner to present the engineer with a proposed certification form drafted by a lender or requested by the local building department.  Execution of the form is often couched as a condition to receipt of final payment for the engineer’s services.  Frequently the proposed form contains representations or certifications by the engineer that the project has been built in strict conformance with the plans and specifications or other language that can be construed as a guarantee or statement of fact as opposed to professional opinion.  In the environmental context, the proposed form may contain representations or warranties that the property is free of environmental contamination.

Certifications, representations warranties or guarantees of this kind may be quite problematic for the engineer or consultant.  In the first place, they may be much more definitive statements than the engineer or consultant can reasonably make based on their actual knowledge of site conditions.  A geotechnical engineer who has observed the compaction of building pads or the placement of drainage lines on an “on-call” or periodic basis is not in a position to state as a fact that the work was performed in strict accordance with the plans and specifications. Thus the engineer may find themselves liable either under a theory of express warranty or negligent misrepresentation.  Where the theory is express warranty there may be no insurance coverage as the engineer may have performed their services in a manner consistent with the standard of care but then made  a positive statement of fact giving rise to liability if it turns out not to be accurate.

The drafting solution to this problem is for the engineer or consultant to first avoid any express representations or warranties in the contract.  Indeed, the engineer or consultant should disclaim all warranties express or implied. Most courts have held that implied warranties of merchantability or fitness for a particular purpose do not apply to design services including engineering and environmental consulting. Secondly , the contract should specify that the form of any certification or warranty must be provided to the consultant in advance of contracting, thus giving the consultant a chance to review and propose modifications to the proposed form of certification or alternatively adjust their scope of work so that they are on site a sufficient amount of the time during construction to permit broad statements about compliance with the contract documents.  Finally, all certification statements must clearly state that the certification is a statement of professional opinion and should set forth the bases for the opinion such as the frequency of site visits, etc.

Dispute Resolution

The value of Alternate Dispute Resolution(ADR) is well known to the members of the Forum.  The pros and cons of the various forms of ADR are beyond the scope of this paper and presentation.  We recommend that all contracts contain a provision specifying some form of ADR, with the precise form dependant in part upon the particular client’s preferences and the nature of the project involved.  However in all contracts we provide that before either party can initiate either arbitration proceedings or litigation the parties must participate in a mediation.  We further typically provide some time limit on the mediation process to prevent one party from dragging out the mediation process to avoid litigation or arbitration.

While “forcing” parties to mediate a dispute before filing suit or an arbitration demand will not resolve a case where one party is not ready to do so, such a provision does slow down the rush to the courthouse or AAA office

A variation that has recently been getting a lot of attention in California is the use of a procedure for the appointment of a judicial referee under the code of civil procedure.23 Under this statute, the parties by written agreement, either the project contract or a separate stipulation can agree to the appointment by the court of a referee who will hear the dispute.  The referee can be a single individual or a panel of three.  The referee or referee must be agreed to by the parties and in practice this is typically a retired judge or experienced private arbitrator.  The individual may be named in the contract or a process for their selection set forth.

Once appointed the referee is empowered to hold hearings and make determinations of all issues of fact or law unless the parties have specified differently in their agreement.  The proceeding is conducted pursuant to the California Code of Civil Procedure and Evidence Code which means the same pretrial discovery rules and motion practice apply.  Parties must comply with the rules of evidence at the hearing.  Once the referee has completed the hearing he is required by statute to provide a written decision which “In the case of a consensual general reference pursuant to Section 638, the decision of the referee… upon the whole issue must stand as the decision of the court… judgment may be entered thereon in the same manner as if the action had been tried by the court.”24

Like binding arbitration a judicial reference provides for a hearing by a mutually agreeable individual or panel that can be conducted in a time frame unaffected by the congestion and constraints of the court calendar and of course without a jury trial.  A perceived advantage over binding arbitration is that the decision is appealable and reviewable by appellate courts for error and thus avoids the concern over a runaway award or decision totally contrary to law.  For those parties and practitioners that are more comfortable with full discovery and the rules of evidence, the referee is required to abide by those requirements.

One obvious disadvantage of the system is that unlike an arbitrator, the referee is not empowered to closely regulate the proceeding by limiting discovery.  Absent stipulation, the parties are free to engage in all of the discovery authorized by the applicable rules of civil procedure including depositions, interrogatories, etc.  Another possible disadvantage depending upon your viewpoint is that since the referee’s decision is appealable once final, the process does not provide finality as quickly as does binding arbitration.  There may be some difficulty in finding the appropriate referee with both the expertise in construction desired by the parties and the legal background to make decisions and write an opinion that will withstand legal scrutiny before the Court of Appeals.

With those concerns noted, the referee process provides a third avenue for those who want the advantage of selecting the trier of fact while preserving their rights to conduct discovery, operate under the rules of evidence and retain the right to appeal a decision they believe is wrong on the law.

Conclusion

Geotechnical and environmental consultants are required to provide professional opinions about subsurface conditions based on a limited number of borings, probes, wells  or trenches.  The variability of the subsurface is such that encountering differing conditions during construction is not uncommon often with significant cost ramifications.  In today’s litigious climate, it is easy to second guess the judgment of the engineer or consultant. 

To protect themselves against claims, engineers and consultants should propose overly conservative designs and recommendations unless adequately protected against unfounded lawsuits or arbitration demands.  Society is not served by owners incurring the cost of over-designed foundations or costly soil removal cleanups when less costly designs will work in the vast majority of circumstances.  It makes sense therefore for owners and their consultants to agree on a risk allocation in their contracts that  protects the owner against professional negligence but does not require the consultant to “bet their company” on every project or assume more risk than they can insure.  Such a fair allocation, when properly communicated to the client is ultimately in the best interest of all the project participants.



1 Kaiser Aluminum  v  Catellus, 976 F.2d 1338

2  A copy of AIA contract form is attached as an Exhibit to this paper.

3 Bruner & O’Connor, Bruner & O’Connor on Construction Law, (West 2002); § 14.2, p.876.

4 (former B.A.J.I. 6.37) In September 2003, California approved revised jury instructions that were designed to be more easily understood by the average juror.  The applicable California jury instruction now reads:  “A [insert type of professional] is negligent if [he/she] fails to use the skill and care that a reasonably careful [inset type of professional] would have used under similar circumstances. “

5 (B.A.J.I. 6.37.3)

6 Appeal of Leo A. Daly Co. (Eng.D.C.A. No. 4463, 1984)

7 263 N.W.2d 420, 423-24 (Minn 1978); See Also SME Industries Inc. v. Thompson, Ventulett, Stainback and Associates, Inc.28 P.3d.669, 678 (Utah 2001).

8 Cal. Civ. Code § 2782.5.

9 (1991) 227 Cal.App.3d 705.

10 Id. at 712-713. 

11 Id. at 715. 

12  Id.

13 Id. at 714.

14 Id. at 716.

15Id. at 712, 714

16 Zurich Ins. Co. v. Kings Industries, Inc. (1967) 255 Cal.App.2d 919, 923-925.

17 (1995) 44 F.3d 195. 

18 688 A.2d 159 (N.J. Super. 1996).

19 Id. at 162-63.

20Western Steamship Lines, Inc. v. San Pedro Peninsula Hospital (1984) 8 Cal.4th 100

21 California Civil Code § 3333.2

22  Restatement of Torts Second § 552; Bily v. Arthur Young & Company (1992) 3 Cal.4th 370; Lincoln Alameda Creek v. Cooper Industries, Inc. (1992) 829 F.Supp. 325

23 CCP § 638 et.seq.

24 CCP § 644.

 

    Our Practice Areas